Download Previous Year PTU University Question Paper of Power Plant Engineering BTEE-406 4th Sem Batch 2011 Onwards B.Tech PTU Nov 2018 Question Paper
B.Tech.(EE-2011 Batch)
POWER PLANT ENGINEERING
Subject Code : BTEE-406 Paper ID : [ 57110]
Time : 3 Hrs. Max. Marks : 60
INSTRUCTIONS TO CANDIDATES : 1. SECTION-A is COMPULSORY consisting of TEN questions carrying TWO marks each. 2. SECTION-B contains FIVE questions carrying FIVE marks each and students have to attempt any FOUR questions. 3. SECTION-C contains THREE questions carrying TEN marks each and students have to attempt any TWO questions
Power Plant Engineering 4th Sem Batch 2011 Onwards B.Tech PTU Nov 2018 Question Paper
SECTION-A
Q1. Write Briefly
a) What is the function of air-preheater and reheater in a thermal power plant?
b) Explain governor control used in thermal plants.
c) Explain essential features of a hydro-electric power plant.
d) Describe mass defect and fertile material.
e) What do you understand by Celane number and supercharging?
f) Explain open and close cycle operation of gas turbines.
g) Explain essential features of remote and automatic control of hydro-stations.
h) What are the different kinds of nuclear reactions? Explain their applications.
i) What are the advantages of combined operation of plants?
j) How coordination between different type of power plants is achieved?
SECTION-B
Q2. Attempt any five questions. 5×6=30
Q2. Give classification of steam generators. How selection of a steam generator is I made? Q3. Describe Rankine cycle and regenerative cycle. Q4. What are the different kinds of water turbine available for hydro power plants? Explain the selection procedure. Q5. What is a combustion system? Explain fluidised bed combustion. Q6. Explain sources of pollution from thermal and nuclear power plants. What are the remedial actions to be taken?
SECTION-C
Q3. Attempt any TWO questions. 2×10=20
Q7. a) Draw layout of a hydro power plant.
b) Explain a gas turbine cycle and its calculations. What thermal refinement is applied to a gas turbine cycle?
Q8. Describe the classification of IC engines. Also explain main parts, operation and layout of a diesel power plant.
Q9. What are the main parts and working of a nuclear power plant with the help of its layout?What are the various safety measures taken?
Sources of pollution from thermal and nuclear power plants.
What are the remedial actions to be taken
Power Plant Engineering 4th Sem B.Tech PTU Nov 2018 Question Paper
Power Plant Engineer
ing 4th Sem B.Tech PTU April 2019 Question Paper
Get Started
https://www.youtube.com/watch?v=UHX6f8TIvX8https://www.youtube.com/watch?v=M_RR6LVICp0https://www.youtube.com/watch?v=mV41CMWonN4https://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0s
Main parts and working of a nuclear power plant with the help of its layout
Various safety measures taken
Electromagnetic Fields 4th Sem B.Tech PTU April 2013 Question Paper
MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
ER.JASWINDER KUMAR
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
ENGINEERING CLASSES
ER.JASWINDER KUMAR
er.jaswinder kumar
Senior Lecturer